Playground Improvements
Playground Improvements
Ro Park Safety Surface
Installation of safety surfacing under the new and existing structures is underway. Landscape refurbishment will be delayed until the fall to increase chance for successful establishment of new plant material.
Playground still remains closed during construction but we are on track to open the playground July 1.
North Orange Aquatic Center
A big thank you to our Township Parks staff for applying fresh mulch in front of the Aquatic Center. Other improvements that have taken place at the Aquatic Center is the offseason is miscellaneous concrete repairs on the pool deck, audio system upgrades and upgrades to the front desk area that will hopefully make check-in more efficient for our pool members and their guest.
North Orange Park
The sealcoating has been applied on 5/11 to our multi-use paths in and around North Orange Park. Just in time for warm weather walks!
Ro Park
The new playground safety surfacing was laid on 5/11 under the existing playground structures. A reminder the whole playground is closed until construction is fully wrapped up.
Walker Woods Park
Installation of new safety surfacing is complete. Playground reopened on April 19th, 2022.
Ro Park
Midstates Recreation has erected the new playground components on April 25th, 2022. The installation of safety surfacing, walkway paving, landscape refurbishment, and site restoration remain. Anticipate entire play area to be open no later than July 1st, 2022.